1. Can the PLC of FX1N be extended to connect with FX2N's input and output modules, positioning modules, analog modules, etc.?
The PLC of the FX1N is fully capable of expanding the expansion modules connected to the FX2N. Such as FX2N-16EX, FX2N-16EYR, FX2N-4AD, FX2N-10GM, FX2N-20GM, etc
2. Does FX PLC have a clock function?
FX1S, FX1N, FX1NC, FX2N, FX3U, FX3UC, FX3G have built-in clock function; The FX2NC can be fitted with an option card with clock function.
3. Will the program be lost after the PLC is powered off?
FX1S, FX1N, FX1NC, FX3G programs are saved by EEPROM, and the programs will not be lost after power failure; FX2N, FX2NC, FX3U, FX3UC programs are supported by the battery, if the battery is low alarm when replacing, the program will be lost; No low battery alarm, will not be thrown away.
4. What is the difference between FX3U-ENET-L and FX3U-ENET-ADP, AND CAN THEY REPLACE EACH OTHER?
FX3U-ENET-ADP is an Ethernet port adapter, and FX3U-ENET-L is an Ethernet module. -L is powerful and can replace ADP; On the contrary, whether it can be replaced or not should be judged by referring to whether the functions used can be satisfied.
1: ENET-ADP and ENET-L both have MC protocol (that is, Mitsubishi PLC special protocol), which is used by the upper industrial computer to read, write and control the PLC using the MC protocol
2: ENET-ADP and ENET-L both have MELSOFT connection function, which is connected to the human-machine interface through the Ethernet port, such as Mitsubishi and Weilun touch screens
3: ENET-L module has a lot of buffers, with the function of buffer sending and receiving (1024 words/time), can be used as the master station to communicate with third-party equipment such as instrumentation, etc., ENET-ADP is only a communication expansion port, without this function
5. Will the program be lost when the PLC replaces the battery?
Within 20 seconds of unplugging the battery socket, plunge into the socket of the new battery, and the program will not be dropped. If the battery LED is left for a long time after the battery LED is lit, the voltage of the battery may be lower than the specified value before the exchange. In this case, when the PLC's power supply is blocked, the program disappears.
|
More on that
|
Application of Mitsubishi FX PLC in speed measurement
[Example] a motor is equipped with an optical encoder (the optical encoder is coaxially installed with the motor), and the FX2N-32MT is used to measure the speed of the motor.
【Solution】
Because the photoelectric encoder is coaxially installed with the motor, the ...
|
|
Confirmation and clearing of Mitsubishi inverter alarm history
When the FR-CS80 inverter detects an abnormality, it will display an error message or alarm in the operation panel according to the abnormal content, or maintain the function action and block the output of the inverter. When maintaining a function operation, please deal with the cause of its operation before resetting the inverter, and then start working. ...
|
|
The difference between Mitsubishi PLC and Siemens PLC
The programming philosophy is different
Mitsubishi PLC is a Japanese brand, programming is intuitive and easy to understand, and it will be easier to learn, while Siemens PLC is a Germany brand, the instructions are more general, it is more difficult to learn, but there are fewer instructions, and Mitsubishi has more instructions, so learn Mitsubishi and learn Siemens' week ...
|
|
Mitsubishi PLC's method of controlling the inverter
1. Mitsubishi PLC's analog signal control inverter
Hardware: FX1N, FX2N PLC hosts, equipped with 1 simple FX1N-1DA-BD extended analog output board; or analog input-output hybrid module FX0N-3A; or FX2N-2DA with two outputs; or four outputs ...
|
|
Advantages and disadvantages of different output types of Mitsubishi PLC
The three output types of PLC are: transistor output, thyristor output and relay output, what is the difference between these three different output types?
(1) Transistor output:
The biggest advantage is that it is accustomed to high-frequency action, and the echo moment is short, generally about 0.2ms, but it ...
|
|
The working principle of the servo motor of the Mitsubishi CNC system
1. The servo mainly relies on the pulse to position, basically it can be understood in this way, the Mitsubishi CNC system maintenance servo motor receives a pulse, and it will rotate the angle corresponding to the pulse, so as to achieve displacement, because the servo motor itself has the function of sending out pulses, so the servo motor ...
|
|
Mitsubishi servo motor types and advantages
1. DC servo
The structure is simple and easy to operate. However, considering the actual operation, the DC servo motor has introduced mechanical equipment for reversing installation, which increases the cost, has many problems, and is inconvenient to maintain, and often interferes with the production and manufacturing due to the sparks of carbon brushes, and electromagnetic interference will occur. Combine...
|
|
Mitsubishi PLC adjusts the built-in time
1. TWR (Time Write) command
Write the time preset value to the built-in real-time clock: Clock information is written to the TWR (Time Write) command. The sequence number of the action instruction is FNC167, [S ·] T, C and D can be used, and only 16-bit operations can be used, accounting for 5 program steps.
The work of the directive ...
|
|
Mitsubishi PLC command negation, empty operation and END, etc
Introduction to Mitsubishi PLC directives such as negation, air operation and END
The INV (Inverse) command is represented by a short 45° slash at the top of the ladder diagram, which negates the result of the operation before the execution of the instruction, and the result of the operation is 0 ...
|
|
Mitsubishi PLC communication detection steps
When you are ready to communicate through AJ71QE71, perform the ping procedure in MS-DOS mode to check if the connection is correct before the Mitsubishi PLC's GPPW starts to communicate. Support communication with Weilun touch screen through serial port.
Under...
|
|
Z series and A200 series inverter fault solving
Low-power Z024 series inverter, our common problems include OC, ERR, no appearance, etc. There are two possible causes of OC.
(1) Aging of the drive circuit
Because the use of a long period of time will inevitably lead to the aging of components, which will cause the driving waveform to occur.
|
|
Troubleshooting methods for Mitsubishi overload
1. Check whether the motor is heated
If the temperature rise of the motor is not high, the first thing to check is whether the electronic thermal protection function of the Mitsubishi inverter is preset reasonably, if the Mitsubishi inverter still has margin, the preset value should be relaxed; For example, the allowable current of Mitsubishi inverter is now out of margin, not ...
|
|
The relationship between torque and performance of Mitsubishi servo motors
1. Additional torque
The torque that occurs on the motor shaft under additional voltage, extra load is called the extra torque of the motor.
2. Starting torque
The torque generated by the motor at the moment when a voltage is applied to the motor in a stopped condition is called the starting torque. The starting torque characterizes the electrical...
|
|
Mitsubishi inverter control method
There are several ways to classify Mitsubishi inverters:
According to the classification of the main circuit operation method, it can be divided into voltage-type inverter and current-type inverter; According to the classification of switching methods, it can be divided into PAM control inverter, PWM control inverter and high carrier frequency PWM control inverter;
Depend on...
|
|
Mitsubishi PLC login password setting operation
Method 1
1. Hit the PLC from RUN to STOP
Mitsubishi's PLC has a special method of setting landing keywords, and it is necessary to ensure that the PLC is in a state of shutdown in order to successfully write the landing keywords.
In the run running condition, the performance of the write will appear "Unable to ...
|
|
Mitsubishi PLC set and reset command use example
1 SET Directive
The SET instruction is called an enthronement instruction. Its function is: to drive the coil, so that it has a self-locking function, and insists on the connection condition. In the diagram, when the moving contact X0 is closed, the SET command is executed to turn on the Y0 coil. After X0 is disconnected, the Y0 coil continues to insist on the ON condition, ...
|
|
Mitsubishi PLC network structure
1. The equipment layer/fieldbus CC-Link equipment layer is a field network that connects PLC and other control equipment, sensors and drive equipment, which is the lowest layer of the entire network system. CC-Link fieldbus connection is selected, the number of wiring is greatly reduced, and the maintainability of the system is improved. Combine...
|
|
The solution to the influence of Mitsubishi inverter on the motor
Generally, asynchronous motors are planned according to constant frequency and constant voltage, and it is impossible to completely adapt to the requirements of frequency conversion speed regulation. The following is the influence of the inverter on the motor:
Regardless of the form of the inverter, the building automation training device operates ...
|
|
Inverter life extension method - Mitsubishi
First, the frequency converter should not be installed on the equipment with a sensation, because the main circuit connection screw in the frequency converter is simply loose, and many frequency converters are damaged due to this reason.
Second, the wiring problem: the input end of the inverter is connected to an air The initial maintenance current should not be too large, ...
|
|
Introduction to the Mitsubishi FX PLC Outage Service
1. What is suspension?
The so-called suspension refers to the fact that in the process of sequentially performing the program scanning, when there is a request to respond immediately, the scanning work performed at that time is immediately suspended, and the service work specified in the request is performed first. When the service job is complete, go back to ...
|
|