1. What is a communication protocol?
A communication protocol is an agreement between two parties to a communication. The agreement includes uniform provisions on data format, synchronization mode, transmission speed, transmission steps, error detection and correction mode, and control character definition, etc., which must be complied with by both parties to the communication. Therefore, it is also called the communication control procedure, or transmission control procedure, which belongs to the data link layer in the ISO'SOSI seven-layer reference model. Hollysys supports ProfiBus, FF, CanOpen, Lonworks, etc
2. What should I do if there is a problem with the on-site signal?
The problems of on-site signals are mainly as follows
Bad measuring element;
transmitter failure;
Connection problems, including signal wire reverse, loose, disconnected, grounding during transmission, and interference during transmission that is affected by interference coupling beyond the system can accept, etc.
In short, from signal measurement, transmission, to MACS terminals, any error in the link will result in incorrect data display.
3. How to check for hardware failure?
Hardware failures often manifest themselves in the following ways
The plug-in board of the module is not tightly plugged into the bus baseplate;
DIP switch error; The communication line is wired in the wrong direction;
The terminal matcher is not connected;
The type of hardware jumper does not match the actual signal requirements;
The system power supply and field power output in the cabinet are incorrect;
The hardware itself is bad.
The results of the above problems are as follows:
After powering on, the hardware board pole is faulty (the indicator light shows the wrong status);
The device is not working;
The system is working, but the displayed corresponding measurement point value is incorrect, the output of the system cannot drive the field device, and so on.
4. How to deal with software errors?
Problems arise due to incorrect coordination between software configuration and hardware
The configuration of the database point does not match the field signal connected to the corresponding channel;
The mouse driver is added to the COM1 port, which makes the system unable to be operated with the mouse when it is running online.
The printer does not print, etc.
5. What problems should I pay attention to when changing the connection joint?
Connector issues
The connector is not welded or the welding is not good, resulting in virtual welding;
Thermal cycling loosens the joint;
Loosening of bolted joints due to vibration;
Poor contact at the connection points due to corrosion.
6. What are the aspects of power failure?
Power issues
Power supply problems are divided into power connection problems and power quality problems.
Problems with the power supply
Including: no connection (fire, earth, zero items, one of which is not connected); Incorrect connection (live wire and neutral wire reversed, ground wire and neutral wire reversed, ground wire and neutral multipoint short).
Power quality issues
Including: the quality of the equipment connection (each connector is loose); The technical indicators (voltage, frequency, etc.) exceed the specified requirements.
Line quality issues
Including: increased impedance of the power cord and poor insulation.
The problem of the poles
Including: the resistance of the ground pole increases, and the earth pole is disconnected from the ground grid.
Environmental issues
Including: the wiring of the power cord, especially the ground wire, is unreasonable, and the wires and equipment that produce strong magnetic field interference are too close.
7. What should I do if the data of an input channel is abnormal?
Solution: Disconnect the field signal of this channel from the terminal of the I/O module, send a signal with the analog signal source and add the same signal as this field signal to this channel, and observe whether the displayed value on the CRT returns to normal. If it is normal, it means that the problem is on the side of the field signal, and it can be found and solved according to the method mentioned above; If it is still abnormal, the problem is caused by the MACS system.
|
More on that
|
HollySys PLC - the usage and principle of PLC programming interrupts
When the PLC understands the interrupt function, it needs to understand the PLC's operating cycle or scan cycle. It is necessary to talk about the process of PLC sequential control loop execution, which is a prerequisite for understanding interruptions and must be mastered. It is divided into three parts, input processing, program processing, and output processing.
1、 ...
|
|
Hollysys DCS - Introduction to the hardware architecture of DCS distributed control system
DCS usually adopts a hierarchical and progressive structure, each level is composed of several subsystems, and each subsystem achieves a number of specific finite goals, forming a pyramid structure. Examining the hierarchical structure of DCS, DCS level and control management level are the two most basic links that make up DCS.
Process control...
|
|
Hollysys PLC - PLC should be noted in operation (2)
2. Interference in the control system and its sources
On-site electromagnetic interference is one of the most common factors in PLC control system and most likely to affect the reliability of the system. It is therefore essential to know the source of on-site disturbances ...
|
|
Hollysys PLC - Six Fault Types of PLC and Troubleshooting Methods (4-6)
Fourth, the fundamental sequence of repairing PLC.
1. Start first.
1) When repairing the PLC, do not start directly immediately, but first ask about the situation and the phenomenon of the problem before and after the problem;
2) If you repair an unfamiliar PLC, you should first understand its operating principle.
...
|
|
Hollysys successfully signed a contract with Luxi Chemical for a 1.2 million tons/year bisphenol A plant project
Recently, Hollysys successfully signed a contract with Luxi Chemical Group Co., Ltd. (hereinafter referred to as Luxi Chemical) for a 1.2 million tons/year bisphenol A equipment project. The project is a key project in Shandong Province in 2021, which will not only greatly improve the competitiveness of Luxi Chemical polycarbonate in the industry, but also have a significant impact on China's phenol ...
|
|
Hollysys DCS control system configuration process
1. Preliminary preparations
Engineering configuration is operated at the engineer station, and before engineering configuration, it is necessary to have the necessary tools and information, specifically:
Tools: refers to the hardware environment and software environment used in engineering configuration, usually refers to the ...
|
|
Hollysys DCS - DCS common communication faults and solutions
01 Node bus failure
The node bus material is usually a coaxial cable, so as long as there is a cable disconnected, the communication of all devices on the bus will be paralyzed, which will cause serious phenomena such as data loss, equipment stoppage and operation interruption, and may eventually directly or indirectly cause huge ...
|
|
HollySys PLC - What are the design requirements that need to be met for PLC programs?
Simplicity
Make the PLC program as simple as possible. Simplicity means using a standardized procedural framework as much as possible and using simple instructions as much as possible.
If you want the program to be simple, in a big way, you should optimize the program structure, simplify the program with process control instructions, and ...
|
|
Hollysys DCS - DCS fault maintenance measures
Whether it is a new unit or an upgraded DCS, the equipment of the system and controller should focus on the reliability and load factor (including redundancy) objectives. The load rate planning of the communication bus must be controlled within a reasonable range, and the load rate of the controller should be balanced as much as possible.
|
|
Hollysys PLC - PLC maintenance and use skills
With the development of society, PLC programmable controller has been widely used in industrial production, but its maintenance and overhaul methods and skills, many engineers are not lawful, the following is to introduce the experience and skills of PLC use process.
1. PLC input and output
A ...
|
|
Hollysys PLC - PLC is classified according to function
According to the different functions of PLC, PLC can be divided into three categories: low-grade, mid-range and high-end.
(1) Low-grade PLC
Low-grade PLC has basic functions such as logic operation, timing, counting, shifting, self-diagnosis, monitoring, etc., and can also have a small amount of analog input/output, arithmetic operation, math...
|
|
Hollysys PLC - How to maintain the PLC control cabinet?
1. Data backup
When carrying out maintenance, we must cut off the power, data backup between power outages is an important link, for the data that needs to be archived for a long time, you can back up the historical trend data to the mobile hard disk, and then turn off the Windows-based operating system (Note...
|
|
Hollysys PLC - the top ten comprehensive failure causes of PLC
1. Grounding problems
The grounding requirements of the PLC system are relatively strict, and it is best to have an independent dedicated grounding system, and it should also be noted that other equipment related to PLC should also be reliably grounded.
When multiple circuit grounding points are connected together, unexpected currents can be generated, resulting in logic errors or ...
|
|
Hollysys signed a contract with Lysys for the integrated management platform project of smart tunnel of Linzhou-Changzhi Expressway in Henan
Recently, Hollysys signed a contract for the comprehensive management platform project of smart tunnel of Linzhou-Changzhi Expressway in Henan Province. Linzhou to Changzhi Expressway is a traffic artery that crosses the Grand Canyon of Taihang Mountain, through Henan and Shanxi, with a total of 7 pairs (14) tunnels.
|
|
Hollysys released a new 100% localized system
On the morning of October 20, 2021, at the Epec Industrial Products Exhibition, Hollysys released a new 100% localized system - 'HOLLiAS MACS IC fully autonomous and controllable DCS system'.
The system integrates the controller microkernel architecture independently developed by Lisi, embedded ...
|
|
Hollysys successfully signed the first 100 billion cubic meter gas field project in Bohai Bay to help achieve the "double carbon" goal
Recently, Hangzhou Hollysys Automation Co., Ltd. successfully signed the first 100 billion cubic meters of gas field project in Bohai Bay (1) - CNOOC Tianjin Branch Bozhong 19-6 condensate gas field phase I development project (hereinafter referred to as: Bozhong 19-6 project), and will provide PCS (DCS), ESD, FGS, ...
|
|
Hollysys PLC - what are the commonly used networking methods of PLC?
1 Universal serial port module
Based on the serial port communication module to realize the network connection, the network structure is shown in Figure 1, the form of computer link is adopted, the corresponding settings are carried out in the configuration software of the host computer, and the communication can be carried out with multiple PLCs without programming, and the FXlS of Mitsubishi ...
|
|
and Lisi PLC - the difference between PLC and inverter
1. The role is different
A PLC (Programmable Logic Controller) is an electronic system designed for digital operations in an industrial environment.
The inverter is the application of frequency conversion technology and microelectronics technology to control the AC motor by changing the frequency of the motor working power supply.
|
|
Hollyps PLC - the control method of PLC and frequency converter connection
1. Use the analog output module of the PLC to control the analog output module of the inverter The analog output module of the PLC outputs a 0-5V voltage signal or a 4-20mA current signal, which is used as the analog input signal of the inverter to control the output frequency of the inverter. This control method is simple to wiring, but it needs to be selected and changed.
|
|
Hollysys PLC - the output wiring of PLC
(1) There are three forms of programmable controller: relay output, thyristor output, and transistor output.