Hollysys PLC - How to maintain the PLC control cabinet?

Create Date: 2024-8-30 12:03:23|Source: HollySys/HollySys

1. Data backup

For the data that needs to be archived for a long time, you can back up the historical trend data to the mobile hard disk, and then turn off the Windows-based operating system (pay attention to saving) and record the internal parameters of the controller.

2. Turn off the power

After the data backup is completed, the operation of pulling the brake should be performed to close the protection switch of each subordinate controller first, and the order is reversed when the main switch is disconnected and powered on. It is best to add a safety lock to prevent someone from accidentally sending power and causing an accident.

3. Appearance and environmental inspection

Check whether the temperature and humidity of the surrounding environment are reasonable, whether there is a large amount of dust on the components, test the insulation of the system, and use the shake meter to test the insulation of the equipment.

4. Control cabinet cleaning

Before cleaning, it is best to cover the electronic components with heat dissipation holes such as PLC and inverter to prevent dust from entering and affecting the work of components. Only use a vacuum cleaner, not compressed air, which will blow dust and water vapor into the components, causing a short circuit.

5. Check whether each line is loose

Be sure to check the looseness of the line, once the line is loose, the controller will not work normally because of the poor contact, and it is very easy to burn out the line.

6. Component inspection

Check whether each component is working normally, and replace it in time if damaged.
Hollysys PLC - How to maintain the PLC control cabinet?

More on that
Hollysys PLC - several common types of PLC control systems Hollysys PLC - several common types of PLC control systems

1. Stand-alone control system The stand-alone control system is controlled by one PLC to control one device or one simple production line, as shown in Figure 7-1. The composition of the stand-alone control system is simple, the number of I/O points required is less, the storage capacity is small, and when the model of PLC is selected, whether there is a communication network at present.

Hollysys DCS - Introduction to DCS grounding classification Hollysys DCS - Introduction to DCS grounding classification

In general, DCS control systems require two types of grounding: protective ground and working ground (logical, shielded, etc.). For systems equipped with safety barrier explosion protection measures, such as those used in the chemical industry, intrinsically safe premises are also required. 2.1 Protected areas (CG, Cabinet Grounding...)

Hollysys DCS – the steps for DCS to properly power off and power on Hollysys DCS – the steps for DCS to properly power off and power on

DCS is properly blacked out When the DCS needs to be powered off for maintenance due to overhaul or other reasons, we often directly power off the DCS, but sometimes this non-standard operation will bring serious consequences, such as configuration loss, PID parameter loss, etc. So there is a need for blackouts and re-on...

Hollysys PLC - PLC is classified according to function Hollysys PLC - PLC is classified according to function

According to the different functions of PLC, PLC can be divided into three categories: low-grade, mid-range and high-end. (1) Low-grade PLC Low-grade PLC has basic functions such as logic operation, timing, counting, shifting, self-diagnosis, monitoring, etc., and can also have a small amount of analog input/output, arithmetic operation, math...

Hollysys PLC - the design specification of PLC program Hollysys PLC - the design specification of PLC program

(1) Select the appropriate PLC model and I/O points, and select the special function module when there are special function requirements. (2) Familiar with the selected PLC programming instructions and compilation software. (3) Carry out soft component planning, including internal relays, holding relays, data registers, ...

HollySys PLC - What places should be avoided when installing PLC? HollySys PLC - What places should be avoided when installing PLC?

(1) The ambient temperature exceeds the range of 0-50 °C; (2) The relative humidity exceeds 85% or there is dew condensation (caused by sudden temperature changes or other factors); (3) direct sunlight; (4) There are corrosive and flammable gases, such as hydrogen chloride, ...

Hollysys PLC - five characteristics that become a necessary condition for high-end PLC Hollysys PLC - five characteristics that become a necessary condition for high-end PLC

Since the day of the birth of PLC, it has occupied the core position of the entire automatic control system. There are also many discussions about the development direction of PLC, whether it is predicted that PAC will replace PLC from 10 years ago, or during this time, some people even say that PLC is no longer needed in the future Industry 4.0 era...

Hollysys PLC - the isolation technology of the input/output loop of the PLC control system Hollysys PLC - the isolation technology of the input/output loop of the PLC control system

1. Circuit isolation The isolation of analog circuits is more complex, mainly depends on the accuracy requirements of the transmission channel, the higher the accuracy requirements, the higher the cost of the channel; However, when the performance requirements rise to the main contradiction, the isolation components should be selected based on performance, and the ...

What are the characteristics of Hollysys PLC - PLC program? What are the characteristics of Hollysys PLC - PLC program?

1. Correctness (low debugging cost) First of all, the PLC program must be able to work correctly to meet the requirements of the actual control process. This is the essence of the PLC program, and if you don't do that, nothing else makes sense. 2. Reliability (low maintenance cost) Not only to ...

Hollysys PLC - common causes and treatment methods of PLC failures in operation Hollysys PLC - common causes and treatment methods of PLC failures in operation

1. Peripheral circuit component failure This type of failure often occurs in the failure of the PLC after a certain period of work. In the PLC control loop, if there is a component damage fault, the PLC control system will immediately and automatically stop working. The input circuit is a PLC that accepts switching quantities, analog ...

and Lisi plc - the difference between DCS and PLC and Lisi plc - the difference between DCS and PLC

The choice between a programmable logic controller (PLC) and a distributed control system (DCS) is a case-by-case analysis, as the requirements for the control system vary depending on the application. You can start from the following aspects! PLC and DCS PLC ...

Hollysys PLC - Introduction to the 4 basic concepts of PLC signals Hollysys PLC - Introduction to the 4 basic concepts of PLC signals

Analog signal: refers to a continuous current signal or voltage signal, and analog signal can be divided into standard signal and non-standard signal. Switching signal: It can be divided into active signal and passive signal, which is basically an on-off signal, and can be measured on and off with a multimeter ohm. ...

HollySys PLC – 8 common error types of PLC HollySys PLC – 8 common error types of PLC

Various brands of PLCs have a self-diagnosis function, but the trick of PLC repair is to make full use of this function to analyze and then pinpoint the problem. Sorted out the 8 common types of errors that PLC repairmen need to know when the PLC presents abnormal alarms. 1. CPU abnormality ...

Hollysys released a new DCS control system Hollysys released a new DCS control system

Hollysys' safe and trustworthy DCS control system uses the controller K-CU11 for the K series large-capacity trusted controller module, which adopts advanced PowerPC architecture high-performance main processor and security components based on national cryptography algorithm, and has the security functions of static trusted start and dynamic trusted measurement. ...

Hollysys released a new 100% localized system Hollysys released a new 100% localized system

On the morning of October 20, 2021, at the Epec Industrial Products Exhibition, Hollysys released a new 100% localized system - 'HOLLiAS MACS IC fully autonomous and controllable DCS system'. The system integrates the controller microkernel architecture independently developed by Lisi, embedded ...

Common fault parts and maintenance of Hollysys PLC Common fault parts and maintenance of Hollysys PLC

1. Lack of motivation It may sound simple, but it's good to check the simple stuff first. Thoroughly inspect all power connections and cables for damage that could cause a short circuit. Make sure your power supply is functioning properly. Use a voltmeter to check if the grounding and voltage are correct. 2. Bad ...

Hollyps PLC - the control method of PLC and frequency converter connection Hollyps PLC - the control method of PLC and frequency converter connection

1. Use the analog output module of the PLC to control the analog output module of the inverter The analog output module of the PLC outputs a 0-5V voltage signal or a 4-20mA current signal, which is used as the analog input signal of the inverter to control the output frequency of the inverter. This control method is simple to wiring, but it needs to be selected and changed.

Hollysys DCS - a common fault of DCS Hollysys DCS - a common fault of DCS

1. Field instrument equipment failure: Field instrumentation equipment includes various transmitters, various switches, actuators, loads and components of various temperatures that are directly connected with the production process. If the field instrument fails, it directly affects the control function of the DCS system and the operator's ...

Hollysys PLC - Introduction to the classification of PLC according to the structure and form Hollysys PLC - Introduction to the classification of PLC according to the structure and form

According to the structural form of PLC, PLC can be divided into two categories: integral type and modular type. (1) Integral PLC The integral PLC is a centralized power, CPU, I/O interface and other components in a chassis, which has the characteristics of compact structure, small size and low price. Small PLC ...

Hollysys debuted at the XCon2022 Security Focus Information Security Technology Summit Hollysys debuted at the XCon2022 Security Focus Information Security Technology Summit

On September 19, 2022, the XCon2022 Security Focus Information Security Technology Summit was successfully held in Beijing. More than 10 technical experts, heads of security departments, and front-line security experts from well-known domestic network security enterprises shared in-depth topics at the meeting.

CATEGORIES BYPASS
Customer Service Center

Online Consultation:QQ


ContactContact

Contact: Manager Huang

Contact QQ: 3271883383

Contact number: 13522565663


Scan the code to add WeChat (please save the picture first on the mobile phone)

working hoursworking hours

Weekdays: 9:00-17:00

Holidays: Only emergencies are handled

Contact us

Contact us

Contact number QQ consultation
QQ consultation

3271883383

Company address
Back to top