1. The motor cannot roll after being energized, but there is no abnormal noise, no peculiar smell and smoke.

1. Cause of the problem: (1) The power supply is not connected (at least two phases are not connected); (2) Fuse blowing (at least two-phase blowing); (3) The overcurrent relay is adjusted too small; (4) The wiring of the control equipment is faulty.

2. Problem cleaning (1) Check whether there is a break point at the power circuit switch, fuse and junction box, and correct; (2) Check the fuse model, the cause of the fuse, and replace the fuse; (3) The setting value of the conditioning relay cooperates with the motor; (4) Correct the wiring.

Second, the motor does not rotate after the power is on, and then the fuse is blown out

1. Cause of the problem (1) Lack of one-phase power supply, or the fixed trunk coil is connected in the opposite direction; (2) Phase-to-phase short circuit of stator winding; (3) Grounding of stator winding; (4) The wiring of the stator winding is faulty; (5) The cross-section of the fuse is too small; (5) The power cord is short-circuited or grounded.

2. Problem cleaning (1) Check whether the knife switch has a phase that is not closed, but there is a phase disconnection in the power circuit; Eliminate the problem of reverse connection; (2) Detect the short circuit point and correct it; (3) Eliminate grounding; (4) Detect and correct misconnections; (5) Replace the fuse; (3) Eliminate the address.

3. After powering on, the motor does not rotate and there is a buzzing sound

l. Cause of the problem: (1) There is an open circuit in the stator and rotor windings (one-phase disconnection) or one-phase power loss of the power supply; (2) The beginning and end of the winding lead wire are connected incorrectly or the winding is reversed; (3) The contact of the power supply circuit is loose and the touch resistance is large; (4) The motor is overloaded or the rotor is stuck; (5) The power supply voltage is too low; (6) The small motor is installed too tightly or the grease in the bearing is too hard; (7) The bearing is jammed.

2. Problem removal: (1) Identify and correct the breakpoints; (2) Check the winding polarity; Determine whether the end of the winding is correct; (3) Tighten the loose wiring screws, use a multimeter to determine whether the joints are falsely connected, and correct them; (4) load shedding or detecting and eliminating mechanical problems, (5) checking is also misconnecting the surface connection method of the rule to Y; Whether the voltage drop is too large because the power supply wire is too thin, to be corrected, (6) install it from scratch to make it flexible; Replacement of qualified greases; (7) Correct the bearing.

Fourth, the motor is difficult to start, and when the additional load is loaded, the motor speed is much lower than the extra speed

1. Cause of the problem: (1) The power supply voltage is too low; (2) The surface connection method motor is mistakenly connected to Y; (3) Welding or cracking of cage rotor; (4) The local coil of the stator and rotor is misconnected and reversed; (3) Excessive number of turns added when correcting the motor winding; (5) Motor overload.

2. Problem elimination: (1) Measure the power supply voltage and try to improve it; (2) correction of connections; (3) Check the open welding and breaking points and correct them; (4) Detect the misconnection and correct it; (5) the correct number of turns of rehabilitation; (6) Load shedding.

                              Fault solution for three-phase asynchronous motor - LS power generation

Fifth, the no-load current of the motor is unbalanced, and the three-phase difference is large

1. Cause of the problem: (1) When rewinding, the number of turns of the stator three-phase winding is not equal; (2) The end of the winding is wrongly connected; (3) The power supply voltage is unbalanced; (4) There are problems such as inter-turn short circuit and reverse coil connection in the winding.

2. Problem Sweeping: (1) Winding the sub-winding from the beginning; (2) review and correct; (3) Measure the power supply voltage and try to eliminate the imbalance; (4) Eliminate the winding problem.

6. When the motor is unloaded and overloaded, the ammeter pointer is unstable and swings

1. Cause of the problem: (1) The cage rotor guide bar is welded or broken; (2) Winding rotor problem (one-phase open circuit) or poor touch of brush and collector ring short-circuit device.

2. Problem cleaning: (1) Detect the broken bar and correct it or replace the rotor; (2) Check the winding rotor circuit and correct it.

7. The no-load current of the motor is balanced, but the value is large

1. Cause of the problem (1) When correcting, the number of turns of the stator winding is reduced too much; (2) The power supply voltage is too high; (3) Y is connected to the motor by mistake for Δ; (4) During the installation of the motor, the rotor is reversed, so that the stator core is not aligned and the effective length is shortened; (5) The air gap is too large or uneven; (6) When overhauling and removing the old winding, the thermal dismantling method is improper, which causes the core to burn out.

2. Problem cleaning (1) Rewind the stator winding and restore the correct number of turns; (2) try to recover the additional voltage; (3) Reconnect to Y; (4) Installation from scratch; (3) Replace the new rotor or adjust the air gap; (5) Overhaul the core or calculate the winding from scratch, and add the number of turns appropriately.

8. When the motor is running, the sound is abnormal and there is abnormal noise

1. Cause of the problem: (1) The rotor rubs with the stator insulating paper or groove wedge; (2) The bearing is worn or there are foreign substances such as sand particles in the oil; (3) The stator and rotor core is loose; (4) Lack of oil in the bearing; (5) Air duct tamponade or electric fan wiping the hood, (6) stator and rotor cores rubbing each other; (7) The power supply voltage is too high or unbalanced; (8) The stator winding is misconnected or short-circuited.

2. Problem cleaning: (1) trim the insulation and cut the groove wedge; (2) Replace bearings or clean bearings; (3) Overhaul stator and rotor cores; (4) Refueling; (5) Finishing the air duct; de novo installation device; (6) Eliminate scratches, small rotors in the car if necessary; (7) Check and adjust the power supply voltage; (8) Eliminate the problem of stator winding.

9. The motor oscillates greatly during operation

1. Cause of the problem: (1) Because the gap of the wear bearing is too large; (2) uneven air gap; (3) Rotor imbalance; (4) Twists and turns of the shaft; (5) The core is deformed or loosened; (6) The center of the coupling (pulley) is not calibrated; (7) The fan is unbalanced; (8) Strength of the casing or foundation

No way; (9) The anchor screw of the motor is loose; (10) Cage rotor open welding and open circuit; Wound rotor break; Plus stator winding problem.

2. Problem cleaning (1) Overhaul the bearing, replace if necessary; (2) Adjust the air gap to make it uniform; (3) Calibrate the dynamic balance of the rotor; (4) Straighten the rotating shaft; (5) Proofread the overlapping core, (6) Proofread from scratch to make it conform to the rules; (7) Overhaul the fan, calibrate the balance, and correct its geometry; (8) Carry out reinforcement; (9) Fastening anchor screws; (10) Modify the rotor winding; Fix the stator windings.

10. The bearing is overheated

1. Cause of the problem: (1) Too much or too little grease; (2) The oil quality is not good, and it contains impurities; (3) The bearing is not properly cooperated with the journal or end cover (too loose or too tight); (4) The inner bore of the bearing is painful and rubs with the shaft; (5) The motor end cover or bearing cover is not flattened; (6) The coupling between the motor and the load is not calibrated, or the belt is too tight; (7) The bearing clearance is too large or too small; (8) The motor shaft is tortuous.

2. Problem cleaning (1) add smooth grease (1/3-2/3 of the volume) according to the rules; (2) Replace the clean smooth grease; (3) If it is too loose, it can be corrected with a binder, and if it is too tight, it should be turned tightly, and the inner hole of the shaft journal or end cover should be ground to make it suitable; (4) Repair the bearing cover and eliminate the friction point; (5) Installation from scratch; (6) Proofread from scratch and adjust the belt tension; (7) Replace the new bearing; (8) Calibrate the motor shaft or replace the rotor.

11. The motor is overheated or even smoked

1. Cause of the problem (1) The power supply voltage is too high, which greatly increases the heating of the core; (2) The power supply voltage is too low, the motor is running with additional load, and the current is too hot to heat the winding; (3) When repairing and removing the winding, the hot dismantling method is not appropriate, and the iron core is burned; (4) The stator and rotor cores rub against each other; (5) The motor is overloaded or starts frequently; (6) Cage rotor broken strip; (7) The motor lacks phase and runs in two phases; (8) After rewinding, the winding impregnation paint is insufficient; (9) The ambient temperature is high, and there is a lot of dirt on the surface of the motor, or the ventilation duct is blocked; (10) Electric fan problem, poor ventilation; Stator winding problems (interphase, turn-to-turn short circuits; The internal connection of the stator winding is faulty).

2. Problem elimination (1) reduce the power supply voltage (such as adjusting the tap of the power supply transformer), if it is caused by the fault of the motor Y and Δ connection, the connection method should be corrected; (2) Increase the power supply voltage or change the thick power supply wire; (3) Overhaul the iron core and clean up the problem; (4) Eliminate friction points (adjust air gaps or frustrations, car rotors); (5) load shedding; Operate the start according to the regular number of times; (6) Check and eliminate rotor winding problems; (7) Rehabilitation three-phase operation; (8) The secondary dipping and vacuum dipping process are selected; (9) Clean the motor, improve the ambient temperature, and choose the cooling method; (10) Check and correct the fan, and replace it if necessary; Overhaul the stator windings to eliminate problems.

More on that
How to choose LS contactors How to choose LS contactors

The working form of LS contactor: Generally speaking, after the contactor coil is energized, the entire coil current will generate a magnetic field, which will make the core inside have electromagnetic attraction to attract the core, and make their AC contactor ...

Introduction of LS electric power contactors Introduction of LS electric power contactors

How LS Contactor Works: Generally, after the contactor coil is energized, the entire coil current will generate a magnetic field, which will make the core inside have electromagnetic attraction to attract the core, and let their communication contactor point action normally closed contact disconnect, or close, which ...

Principle of electrical equipment maintenance - LS power generation Principle of electrical equipment maintenance - LS power generation

1. Speak before you start When it comes to faulty electrical equipment, you should not rush into action, but ask about the passage and phenomenon of the fault. For unfamiliar equipment, you should also understand the circuit principle and structural characteristics, and follow the corresponding rules. Before dismantling, it is necessary to fully understand each ...

The size of the contactor is selected by the type of contactor - LS produces electricity The size of the contactor is selected by the type of contactor - LS produces electricity

1. Select the corresponding category of contactor according to the control object, operation times and application category of the contactor. 2. Select according to the rated voltage of the line at the application location. 3. Select the rated current of the main contact of the contactor according to the load capacity. 4. About the voltage level of the lead coil ...

The five stages of mastery of PLC technology The five stages of mastery of PLC technology

One. Logical stage   The so-called logical stage is to be able to complete the general logical planning in the relay system, since it is a relay system, so the knowledge of power drag is the foundation of this stage. I personally summarize that the root of learning the relay system lies in the word "grab", the relay system ...

Inverter air boost test step - LS power generation Inverter air boost test step - LS power generation

1. Download the control program. 2. Put the inverter in open-loop experimental mode and set the appropriate parameters. 3. Connect the incoming cable of the inverter. The cable on the output side of the inverter is not connected. 4. Push the high-voltage cabinet to the experimental position, close the switch, and ...

Variable frequency regenerative braking method - LS generates electricity Variable frequency regenerative braking method - LS generates electricity

1. Energy consumption type This method is to connect a braking resistor in parallel in the DC circuit of the inverter, and control the on/off of a power tube by detecting the DC bus voltage. When the DC bus voltage rises to about 700V, the power tube is turned on, and the regenerative energy is passed into the resistor.

The difference between voltage inverter and current inverter - LS produces electricity The difference between voltage inverter and current inverter - LS produces electricity

For example, the operating principle of voltage inverter is mainly to regulate the voltage source, and the voltage source regulates the current to achieve the role of conditioning, while the current inverter is to directly regulate the current to achieve the role of conditioning. ...

Wiring of the main circuit of the inverter - LS generates electricity Wiring of the main circuit of the inverter - LS generates electricity

1. The power supply should be connected to the R, S, and T terminals at the input end of the inverter, and must not be connected to the output terminal (U, V, W) of the inverter, otherwise the inverter will be damaged. After wiring, it is necessary to clean the trivial wires, which may cause abnormalities, failures and problems, and it is necessary to always keep ...

LS Electric has been selected as one of the "Top 100 Global Innovators" for 10 consecutive years. LS Electric has been selected as one of the "Top 100 Global Innovators" for 10 consecutive years.

In Clarivate's recent statement, LS Electric was named one of the top 100 innovators in the world. The trophy handover ceremony was held in Anyang, LS Electric R&D Park, with Kim Yeong-geun, Chief Technical Officer of LS Electric, and Ahn Seong-sik, CEO of Clarivate Korea, acting as representatives of both parties.

The basic method and steps of inverter debugging - power inverter The basic method and steps of inverter debugging - power inverter

1. No-load energizing test of inverter 1. Ground the grounding terminal of the inverter. 2. Connect the power input terminal of the inverter to the power supply through the leakage maintenance switch. 3. Check whether the factory display window of the inverter is normal, if it is incorrect, it should be reset.

The protection measures of the power generator inverter for the motor The protection measures of the power generator inverter for the motor

The protection of the motor by the power converter mainly includes the following aspects: overvoltage protection, undervoltage protection, overcurrent protection, phase loss protection, inverter protection, overload protection, grounding protection, short circuit protection, overfrequency protection and stall protection. ...

Precautions for the maintenance of the inverter of the tensile testing machine - LS generates electricity Precautions for the maintenance of the inverter of the tensile testing machine - LS generates electricity

In the course of regularly checking the variable-frequency drive (VFD) of the tensile testing machine, we can visually check the operating status directly from the outside. (1) The ambient temperature is normal, and it is required to be between -10°C and +40 ...

The cause of the broken shaft of the motor - LS generates electricity The cause of the broken shaft of the motor - LS generates electricity

1. Improper device: The motor is not concentrious with the equipment being dragged, resulting in excessive radial load on the motor, which eventually leads to metal exhaustion. When the radial load on the extension end of the motor shaft is too large, it will cause the motor shaft to have zigzag deformation in the radial direction. When the motor rotates, the shaft's ...

LG Inverter-LS Inverter-IGXA Sales LG Inverter-LS Inverter-IGXA Sales

LG Inverter LS Inverter IGXA Series ** for sale, its models are as follows: SV004IGXA-4 60210101W0 Power 0.37KW (Input: 3-phase 380V / Output: 3-phase 0——380V)   SV008IGXA-4 6021010 ...

Inverter circuit board repair and drawing-free maintenance method - LS power generation Inverter circuit board repair and drawing-free maintenance method - LS power generation

1. Be "confident" It is necessary to fully understand the principles of some typical circuits and be familiar with them. Guangzhou Kewo Training Center believes that drawings are dead, and the thoughts in the head are alive, able to make analogies, able to reason, and able to touch analogies. For example, switching power supply is always inseparable from ...

The working principle of the LS power production module The working principle of the LS power production module

When the LS power generation module is put into operation, its working process is generally divided into three stages, namely input sampling, user program fulfillment and output rewriting. The completion of these three phases is called a scan cycle. During the entire operation, the PLC's CPU repeatedly performs the upper ...

Calculation method of filter capacitance value of inverter Calculation method of filter capacitance value of inverter

Alternating current can be converted into direct current using rectifier electricity, but in three-phase electricity, this DC voltage or current contains voltage or current ripple with a frequency of six times the frequency of the power supply. In addition, the inverter inverter will also generate ripple voltage or current due to output and carrier frequency, etc., and reverse ...

PLC installation and wiring skills - LS power generation PLC installation and wiring skills - LS power generation

The PLC should be kept away from strong disturbance sources such as electric welding machines, high-power silicon rectifier equipment and large-scale power equipment, and cannot be installed in the same switch cabinet as high-voltage electrical appliances. Power cables, control cables, and PLC power cables and I/O cables should be separated from the wiring ...

The difference between low-speed and high-speed centrifuges – LS generates electricity The difference between low-speed and high-speed centrifuges – LS generates electricity

Through the rational planning of the structure of the low-speed centrifuge, the hygienic dead angle can be effectively eliminated. The transition of the structural parts is smooth, and the surface is polished. External structural components, fasteners, and rollers are made of stainless steel. The housing is a clamshell type, which allows for thorough cleaning of the interlayer space of the centrifuge housing without the need for a bowl ...

CATEGORIES BYPASS
Customer Service Center

Online Consultation:QQ


ContactContact

Contact: Manager Huang

Contact QQ: 3271883383

Contact number: 13522565663


Scan the code to add WeChat (please save the picture first on the mobile phone)

working hoursworking hours

Weekdays: 9:00-17:00

Holidays: Only emergencies are handled

Contact us

Contact us

Contact number QQ consultation
QQ consultation

3271883383

Company address
Back to top