The robot is running a jitter cause check – the KUKA robot

Create Date: 2024-8-30 12:03:23|Source: KUKA

1. Is it that the load data you entered is incorrect?

If the load data is too high or too low, and the difference between the load and the practice load is too large, it will cause flutter!

                                    The robot is running a jitter cause check – the KUKA robot

2. Is there a large turning or posture change in the trajectory of the robot?

Acceleration too fast, be careful to flutter and "roll over"

3. Are the acquiescence parameters of the motor of the robot project correct?

A small number of models of robot motors acquiesce to incorrect parameters and need to update the robot catalog to reconfigure the robot project

More on that
The robot implements the predictive maintenance step – KUKA The robot implements the predictive maintenance step – KUKA

Speculative protection cannot be achieved overnight, but needs to be completed at multiple levels and gradually. The following are the three key steps to start implementing speculative protection in the production equipment, please consult the data application experts of Xiamen Wutong Bolian for specific plans and steps: ...

Definition and application of KUKA industrial robots Definition and application of KUKA industrial robots

Definition: Industrial robot is widely used in the industrial field of multi-joint manipulator or multi-degree of freedom machine device, with a certain degree of automaticity, can rely on its own power and control ability to achieve a variety of industrial processing and production functions. Industrial robots are widely used in electronics, logistics, chemical ...

Frequently asked questions about KUKA robot motors Frequently asked questions about KUKA robot motors

1. KUKA robot motor coil repair, leakage, burning, overcurrent, overvoltage, heating, hot starting, alarm, tripping, and weak work; 2. The servo motor is weak in magnetism repair work, and the low-speed (no-load) can be alarmed at high speed (operation); 3. The repair of the external shaft motor of the robot is encountered.

Introduction to the IF logic of the KUKA robot Introduction to the IF logic of the KUKA robot

1. Enter the program in the form of the teach pendant T1, click on the lower left corner: Instruction - Logic, and you will see the commonly used logic instructions such as WAIT, WAITFOR, and OUT. 2. Select WAIT. The lower end of the interface *** presents the WAIT Time port sec .

KUKA KR 210 R2700-2 maintenance precautions KUKA KR 210 R2700-2 maintenance precautions

1. Power supply in front of the device The problem rate of the power supply is very high in the programming of the KUKA robot in the whole problematic device, so it is easy to overhaul the power supply first. 2. First the general and then the special Faults caused by the quality of assemblies or other equipment faults generally account for the common ...

Precautions for the maintenance of the KUKA KR 210 R2700-2 Precautions for the maintenance of the KUKA KR 210 R2700-2

1. Power supply in front of the device The high rate of defects in the power supply during the programming of the KUKA robot is the entire faulty device, so it is easy to overhaul the power supply first Multiplier. 2. First the general and then the special Faults caused by the quality of assemblies or other equipment faults are common.

KUKA LBR iiwa works hand in hand with workers KUKA LBR iiwa works hand in hand with workers

Dürr AG has developed the KUKA robot cell for human-robot collaboration with KUKA's sensitive LBR iiwa lightweight robot for automated bonding in the final assembly of the passenger car industry. This work unit not only contributes to the advancement of bonding roof antenna bases inside the car ...

KUKA Robot Alternative Package Addition Method KUKA Robot Alternative Package Addition Method

How to use the alternative software package for KUKA robots Teach Pendant Device Method Login Administrator Click Get Operational > Assistive Software Click New Software Click Configure Click Path Picking Select the corresponding folder in the USB flash drive and click Save ...

KUKA Robotics Programming Language KUKA Robotics Programming Language

1. KUKA's programming language KUKA'S ROBOT PROGRAMMING LANGUAGE IS KRL, WHICH IS A TEXTUAL LANGUAGE SIMILAR TO C LANGUAGE (PLEASE BAIDU WHAT IS C LANGUAGE), WHICH IS COMPOSED OF .SRC AND . DAT composition. . SRC stores program logic, instructions, actions, etc. DAT stores azimuth variables in the form of ...

Key components of industrial robots - KUKA robots Key components of industrial robots - KUKA robots

1. High-precision reducer Fine reducer, in the field of mechanical transmission is the central equipment between the power source and the executive organization, usually it puts the power of high-speed operation such as electric motor and internal combustion engine through the pinion on the input shaft and meshes the large gear on the output shaft, so as to reduce the ...

Technological trends in KUKA industrial robots Technological trends in KUKA industrial robots

The robot industry is a fast-growing industry in China for a period of time in the future, as one of the country's new strategic industries, robot skills reflect the comprehensive strength of national science and technology. From 2010 to 2013, the sales of industrial robots in China ...

Introduction to KUKA foundry robots Introduction to KUKA foundry robots

KUKA foundry robots are equipped with high-temperature, corrosion-resistant, acid-and-alkali resistant coatings, which are particularly suitable for the harsh environments of the foundry and forging industry.   Forming, casting and machining: KUKA foundry robots are all-rounders in the foundry and forging industry. KUKA foundry robot can be used in casting and forging ...

Industrial Degrees of Freedom Parallel Robot Applications Industrial Degrees of Freedom Parallel Robot Applications

Parallel organization is mostly used in occasions that require high stiffness, high precision, high speed, and no large space, and the specific uses include: 1. Sorting, transferring, packing and packing in food, pharmaceutical, electronic and chemical industries. 2. Imitate movement; For example, pilots practice simulators in three-dimensional space; Engineering...

The structure of the KUKA robot The structure of the KUKA robot

The structure of the robot with a straight tandem structure is simplified, as shown in the figure below. The six-axis straight tandem robot has six joint axes from A1 to A6, during which A1, A4, and A6 are rotary axes, and other A2, A3, and A5 are swing axes. The robot motion system attaches great importance to the end node of the robot motion chain.

Freedom of choice for welding robots – KUKA robots Freedom of choice for welding robots – KUKA robots

The arms and wrists of the welding robot are the basic parts of the movement. The robot arm of any design has three degrees of freedom to ensure that the end of the arm can reach any point in its working range. The three degrees of freedom of the wrist are the inverse transport of the three axes X, Y, Z perpendicular to each other in space.

KUKA mobile robot KMP 1500 features: KUKA mobile robot KMP 1500 features:

The KUKA AMR KMP 1500 is an omnidirectional mobile channel capable of moving autonomously and sensitively within space. Combined with the new generation of KUKA Sunrise control systems, it offers modular, widely used mobile production plans for the industry of the future. ...

KUKA industrial robot control system functions KUKA industrial robot control system functions

The robot control system is an important part of the robot, which is used to control the manipulator to complete specific work tasks, and its basic functions are as follows: 1. Recall function: store the order of work, the movement path, the movement mode ...

Industrial robot operation technology – KUKA robots Industrial robot operation technology – KUKA robots

Industrial Robot Motion Programming: 1. Understand the industrial robot, the operating environment setting of the teach pendant, and the use of programmable buttons of the teach pendant; 2. Manually operate the robot, the robot I/O communication interface, standardize the I/O board and equipment; 3. Establishment and storage of program data, ...

The use of logical functions in robot programs – KUKA robots The use of logical functions in robot programs – KUKA robots

Inputs and outputs are used for logic programming, and digital and analog inputs and outputs can be used for communication with the peripherals of the robot control system. When programming the KUKA robot, the ...

Classification of industrial robots – KUKA robots Classification of industrial robots – KUKA robots

1. According to the coordinate method of the operating machine, it can be divided into: (1) Cartesian coordinate industrial robots Its moving part is composed of three straight lines moving (i.e., PPP) in a straight line with each other, and its working space is rectangular. Its movement interval in each axis can be carried out in all axes.

CATEGORIES BYPASS
Customer Service Center

Online Consultation:QQ


ContactContact

Contact: Manager Huang

Contact QQ: 3271883383

Contact number: 13522565663


Scan the code to add WeChat (please save the picture first on the mobile phone)

working hoursworking hours

Weekdays: 9:00-17:00

Holidays: Only emergencies are handled

Contact us

Contact us

Contact number QQ consultation
QQ consultation

3271883383

Company address
Back to top