The operation essentials of Schneider disconnectors

Create Date: 2024-8-30 12:03:23|Source: Schneider/Schneider

施耐德阻隔开关特点:首先是施耐德阻隔开关能够用来阻隔电源,它能够将带电设备与高压检修设备断开,还能够在上面看到显着的断开点。其次是施耐德阻隔开关能够与断路器合作,以到达改变系统运转接线方式的意图。施耐德阻隔开关能够接通或者是断开小电流电路。在高压配电装备中阻隔开关应用的比较多一些,它能够很好地确保检修作业的安全。

                                  The operation essentials of Schneider disconnectors

  关于施耐德阻隔开关的操作办法,其分为3个部分。包括阻隔开关合闸、阻隔开关分闸和装有电磁闭锁的阻隔开关闭锁失灵时的操作办法。

  运转人员在履行倒闸操作时,必须仔细查看断路器确真实断开方位。关于三相联动的阻隔开关,三相起落应一起,相差不得大于3mm,方答应进行阻隔开关的分合闸操作。

1. Barrier switch closing operation method

  假如是手动操作,运转人员应先拨出连锁销子后再进行合闸,开端应缓慢,当动触头接近静触头时要迅速合上,以避免发生弧光。假如在合闸开端时就发生电弧,则应立即将阻隔开关合上,制止运转人员将阻隔开关再往回拉,由于回拉将会使弧光扩大,形成设备更进一步的损坏。在合闸终了时用力不行过猛,以避免合闸过深,使支撑瓷瓶受损伤。在阻隔开关合好后,运转人员应仔细查看合闸是否杰出,动触头是否彻底进入静触头内,以避免因接触不良而引起动静触头发热。 关于转轴上反转的阻隔开关,合闸后应使刀片处于垂直固定触头的平面上,这样才干确保触头处的压力和必要的接触电阻;对平开式阻隔开关,合闸后刀片应转至水平方位,其臂应伸直。假如静触头活动帽口偏右,阐明动触头臂锤杆合过了头。

  冬天操作野外阻隔开关时,可用数次接通和断开的办法将触头上的冻冰和霜雪摩擦掉,使阻隔开关合上后能确保动静触头接触杰出。阻隔开关可靠运转的条件就是在阻隔开关有传动设备时,应以其正确的调整来确保;假如没有传动设备,则应以绝缘杆的正确操作来确保。各种规格的阻隔开关均不答应在短路时主动脱落,为此,阻隔开关在合闸方位时,应以五防闭锁设备闭锁着。值班人员需仔细查看这些设备,在每次阻隔开关合闸后用销子将阻隔开关扣住,并将五防闭锁设备锁好,避免阻隔开关主动脱开,形成事端。

2. Operation method of barrier switch opening

  阻隔开关摆开时,开端应慢且慎重些,当动触头离开静触头时,假如发生电弧,运转人员应立即将阻隔开关合上,中止操作。但是在切断小负荷电流和充电电流时,摆开阻隔开关将有电弧发生,此刻应迅速将阻隔开关断开,以便顺畅消灭电弧。在拉闸终了时要缓慢,这是为了避免冲击力对支撑瓷瓶和操作机构的损坏,*后运转人员应查看连锁销子是否销好。在阻隔开关摆开后,运转人员应仔细查看阻隔开关确真实断开方位,断开的空气绝缘距离应合格,并查看动触头的确已拉到止境,并且摆开的角度应契合制作厂家的规定。关于室内阻隔开关,假如断开的绝缘距离不够,应插入绝缘隔板,否则带电侧与停电挂地线的一侧会发生放电短路事端。

More on that
Schneider inverter ATV61 OPF failure analysis Schneider inverter ATV61 OPF failure analysis

Q: 250KW ATV61 with 250KW fan, when decelerating to low speed, OPF (motor missing three-phase) problem will be reported occasionally. There are no contactors or switches between the inverter and the motor. Answer: This situation seems to be a problem with the inverter, which is a false alarm. Not really! The fan is decelerating ...

Precautions for trial operation of Schneider motors Precautions for trial operation of Schneider motors

1. Check during the test run of the motor 1.1 Before the motor starts It is necessary to carefully check whether the insulation resistance is qualified, check whether the wiring of the secondary circuit is correct, and the inside of the motor should be boring, clean and free of debris. Investigate whether the fastening bolts of the motor are loose and the bearing is ...

Schneider touch screen touch deviation causes Schneider touch screen touch deviation causes

(1) Problem 1: Contact deviation Phenomenon 1: The direction of the finger does not coincide with the mouse arrow. Reason 1: After installing the driver, there is no vertical contact with the bullseye when checking the alignment. Deal 1: Correct the position from the beginning. Phenomenon 2: ...

The layout of the inverter is composed of Schneider The layout of the inverter is composed of Schneider

rectifier Many converters use diodes, which convert the power frequency power supply to DC power. It is also possible to form a reversible converter with two sets of transistor converters, because the purpose of the power target is reversible and can be regenerated for operation. Flat wave back After the rectifier rectification ...

The difference between vector inverter and general-purpose inverter - Schneider The difference between vector inverter and general-purpose inverter - Schneider

There are two main differences between vector inverters and general-purpose inverters. One is high control accuracy, and the other is high output torque at low speed. Vector special inverter: The operating principle of the vector special inverter is to carry out inverter after rectification, ...

Inverter selection principle - Schneider Inverter selection principle - Schneider

1. Select the inverter according to the load characteristics. 2. When selecting the inverter, the actual motor current value should be used as the basis for the selection of the inverter, and the additional power of the motor can only be used as a reference. Secondly, the output content of the inverter should be fully considered.

Schneider soft-start ATS48 application range Schneider soft-start ATS48 application range

ATS48 soft starter is used in water treatment, food and beverage, mining metallurgy, power and chemicals. Scope of application: including pump fans and large inertia machine compressor conveyors Advantages: 1. Economical solution Reduce mechanical stress and increase machine availability. 2. ...

Schneider miniature circuit breaker C type D type difference Schneider miniature circuit breaker C type D type difference

The difference between Schneider OSMC32N3D10 and OSMC32N3C10 After type comparison, one is Schneider D10A and the other is Schneider C10A. Schneider circuit breaker type D, suitable for power equipment, such as motor load, air conditioner, etc.; Schneider circuit breaker type C, suitable ...

The difference between high voltage and low voltage of Schneider inverter The difference between high voltage and low voltage of Schneider inverter

1. What is the difference between high-voltage inverter and low-voltage inverter? Frequency converters can be broadly divided into two categories: high-voltage frequency converters and low-voltage frequency converters. In terms of use, the applicable objects are different, and the high-voltage motor is the same from the principle of speed regulation. From the topology ...

Line leakage detection method - Schneider Line leakage detection method - Schneider

Line leakage detection method, leakage check method summary, if a closing, leakage switch will trip, this kind of front leakage, check the method is as follows: 1. Disconnect all the separation gates, close the main gate, close the separation gates one by one, and close them to ...

Schneider inverter debugging steps and brief description Schneider inverter debugging steps and brief description

Commissioning process of the Schneider 61 series 1. Preparations 1. Measure insulation. Connect the power supply side (R.S.T) and the motor side (U.V.W) of the inverter Disconnect the cable, insulate the cable with a 500 megaohm or 1000 megaohm shake meter, and if it meets the requirements, restore it.

Motor control mode of Schneider inverter Motor control mode of Schneider inverter

Fundamentals of magnetic flux vector manipulation The control of a three-phase asynchronous motor is much more complicated than that of a DC motor because the current, voltage, induced potential, magnetic flux, etc., of the stator and rotor are all alternating. However, the stator winding of the three-phase asynchronous motor is a symmetrical three-phase winding, which exerts a ...

Schneider touch screen touch deviation causes Schneider touch screen touch deviation causes

(1) Problem--: Contact deviation Phenomenon 1: The direction of the finger does not coincide with the mouse arrow. Reason 1: After installing the driver, there is no vertical contact with the bullseye center when calibrating the alignment. Deal 1: Correct the position from the beginning. Phenomenon 2: Some districts ...

Schneider considers the safety of lithium batteries from four perspectives Schneider considers the safety of lithium batteries from four perspectives

In China, the trend of UPS switching to lithium batteries will become more and more rapid. As a global leader in data center infrastructure solutions and services, Schneider Electric found that in addition to the purchase price factor, Chinese customers are now choosing the weight of UPS lithium batteries after accurate positioning and inquiry of shopping malls.

Schneider circuit breaker technical issues Schneider circuit breaker technical issues

1. Overload maintenance failure: The circuit breaker should be tripped for maintenance when the current exceeds the rated current, but sometimes the overload maintenance failure may be due to some reasons. This may be due to incorrect overload maintenance settings, long overload periods, thermal aging due to successive overloads, etc. 2 ...

Schneider inverter motor control mode Schneider inverter motor control mode

Fundamentals of magnetic flux vector manipulation The control of a three-phase asynchronous motor is much more complicated than that of a DC motor because the current, voltage, induced potential, magnetic flux, etc., of the stator and rotor are all alternating. However, the stator winding of the three-phase asynchronous motor is a symmetrical three-phase winding, which exerts a ...

How to choose Schneider circuit breaker How to choose Schneider circuit breaker

The origin orientation is incorrect, and the encoder debugs/zeros the bit First, the value of the current at each branch is calculated (1) Purely resistive loads, such as bulbs, electric heaters, etc., are directly divided by the indicated power by the voltage. Formula I = power/220v; ...

NSX molded case circuit breaker selection - Schneider NSX molded case circuit breaker selection - Schneider

The Schneider NSX molded case circuit breaker has a double rotary contact construction for maintenance, and the high-end electronic trip unit allows for accurate measurement and easy communication. Schneider NSX molded case circuit breaker conforms to IEC60947-2, GB14048.2, China's CCC certification and multinational classification certification...

Schneider PLC intelligent parameter features Schneider PLC intelligent parameter features

Characteristic: 1. NEZA PLC (TSX08 series) EZA series is a small PLC with rich functions, high performance-to-price ratio, small size and strong versatility. A new generation of handheld programmer - Chinese PDA PL707WinCE, supports Chinese interface, whether it is programming, ...

How to prevent counterfeiting from Schneider switch sockets How to prevent counterfeiting from Schneider switch sockets

1. Logo The logo of the product is a status symbol, so it will be made very exquisitely. Schneider switches are also very careful in the production of logo, each letter is like an independent work of art, and let's see that the letter "A" is flat and wide. But the imitation ...

CATEGORIES BYPASS
Customer Service Center

Online Consultation:QQ


ContactContact

Contact: Manager Huang

Contact QQ: 3271883383

Contact number: 13522565663


Scan the code to add WeChat (please save the picture first on the mobile phone)

working hoursworking hours

Weekdays: 9:00-17:00

Holidays: Only emergencies are handled

Contact us

Contact us

Contact number QQ consultation
QQ consultation

3271883383

Company address
Back to top