With the inclusion of "exploring the construction of digital twin cities" in the 14th Five-Year Plan, the field of intelligent transportation is being endowed with more new business value. Recently, Century Qualcomm and Hollysys reached a strategic cooperation, based on the principle of "giving full play to advantages, mutual promotion, long-term cooperation, mutual benefit and win-win", the two sides will cut into the three dimensions of new technologies, new applications and new models in terms of smart highways and digital twin tunnels, and jointly create joint products and solutions to comprehensively help the rapid development of smart transportation.
In terms of smart highways, based on the high-precision traffic geographic information platform and big data resource platform, Century Qualcomm integrates multi-source data information such as people, vehicles, roads, environment, and events to realize digital supervision of highway assets, real-time monitoring of traffic operation status, safety risk identification and early warning, and accompanying travel service release. Hollysys has built a smart high-speed cloud control platform to realize high-speed status monitoring, data fusion display, emergency linkage command and application-assisted decision-making. Through the construction of a quasi-all-weather traffic system, intelligent guidance of driving safety, identification of meteorological disasters, and monitoring, early warning and disposal of ice condensation are realized.
The cooperation between the two parties, on the one hand, combines the cloud control platform and the capabilities of the two-dimensional and three-dimensional integrated engine to realize the visual supervision and commercial application exploration of highway cloud control; On the other hand, combined with the quasi-all-weather travel system and high-precision geographic information platform, the comprehensive and accurate monitoring and dynamic management of highway meteorology are realized, the accident rate of expressways and the restrictions caused by bad weather are reduced, and the quasi-all-weather traffic of expressways is improved.
In terms of digital twin tunnels, Century Qualcomm relies on the company's core capabilities such as high-precision maps, 3D models, and domestic self-developed two-dimensional and three-dimensional integrated GIS engines to build a tunnel digital twin system. At the same time, it combines the capabilities of Hollysys in tunnel inspection robots and emergency linkage systems to further strengthen the comprehensive management and control of all elements and cycles of tunnels, and provide stronger support for tunnel safety early warning, emergency command, analysis and decision-making, management and maintenance.
At the same time, based on this cooperation, Century Qualcomm and Hollysys will lead to different scenarios and ecology of expressways through active and forward-looking empowerment, and ultimately drive the sustainable development of expressway transportation towards real-time, collaborative and intelligent, and empower the ecological construction of smart transportation with better solutions.
|
More on that
|
Hollysys PLC - Introduction to the 4 basic concepts of PLC signals
Analog signal: refers to a continuous current signal or voltage signal, and analog signal can be divided into standard signal and non-standard signal.
Switching signal: It can be divided into active signal and passive signal, which is basically an on-off signal, and can be measured on and off with a multimeter ohm.
...
|
|
Hollysys DCS - Introduction to the hardware architecture of DCS
Examining the hierarchical structure of DCS, DCS level and control management level are the two most basic links that make up DCS.
The process control stage specifically realizes the decentralized control functions such as signal input, conversion, operation and output. The controls at the process control level vary in different DCS, ...
|
|
Hollysys HOLLiAS MACS IC helps the localization of large-scale thermal power units
At 15:05 on January 12, 2022, Datang Anhui Luoneng Power Generation Co., Ltd. (hereinafter referred to as Datang Luohe) successfully completed the full-load trial operation of Unit 5 after comprehensive upgrading, marking the smooth operation of Unit 5 of Datang Luohe Power Plant after the transformation. Hollysys HOLLiAS MACS IC completely ...
|
|
Hollysys PLC - the output wiring of PLC
(1) There are three forms of programmable controller: relay output, thyristor output, and transistor output.
(2) The wiring of the output terminal is divided into independent output and common output. When the output relay or thyristor of the PLC is activated, the two output terminals of the same number are turned on. In different groups, you can ...
|
|
Hollysys debuted at the 13th Berlin International Rail Transit Exhibition
On September 20, 2022, Berlin time, the 13th Germany Berlin International Rail Transit Exhibition (InnoTrans 2022) opened at the Berlin International Exhibition Center in Germany. Following the 2018 exhibition, Hollysys once again appeared at the Berlin International Railway Exhibition (hereinafter referred to as the Berlin Exhibition) ...
|
|
Hollysys PLC - Six Fault Types of PLC and Troubleshooting Methods (1-3)
First, the type of failure of the PLC.
1. External equipment failure.
External equipment refers to various switches, sensors, actuators, loads, etc., which are directly connected with the PLC operation process. The failure of these equipment will directly affect the control function of the PLC system. Therefore...
|
|
Hollysys launched an intelligent simulation teaching instrument system to help cultivate industry professionals
In recent years, the State Administration of Safety Supervision, the Ministry of Industry and Information Technology, the Ministry of Education, and the Ministry of Finance have successively launched a number of national policies to implement major decision-making projects such as vocational skills improvement actions, safety skills improvement actions, and vocational education reforms, aiming to create a highland for the training of technical and skilled talents.
|
|
Hollysys PLC - the six application functions of PLC
1. It is used for switching control
The ability of PLC to manipulate switching quantities is very strong. The number of points in and out of the control, less than a dozen points, dozens of points, more can be hundreds, thousands, or even tens of thousands of points, because it can be networked, the number of points is almost unlimited, no matter how many points can be controlled, the control ...
|
|
Hollysys' 100% domestic PLC has achieved breakthrough applications in the field of nuclear power
Hollysys, as the PC general contractor, participated in the construction of the first smart water project in the domestic nuclear power industry (1) - Qin's No. 2 Plant Chengjing Water Intake Smart Operation and Transformation Project, which was recently completed and put into operation. The project is independently implemented by Hollysys, and Hollysys is independently controllable, safe and reliable, and deeply developed by the nuclear high-tech project.
|
|
Hollysys PLC - PLC should be noted in operation (three, four, five)
3. Main anti-interference measures
(1) Reasonable treatment of power supply to suppress the interference introduced by the power grid
For grid disturbances introduced by the power supply, an isolation transformer with a shielded ratio of 1:1 can be installed to reduce the interference between the equipment and the ground.
|
|
Hollysys DCS - the debugging scheme of DCS system
1. Check before power-on
If the cable insulation resistance meets the requirements (greater than 5M ohms), check the cable insulation resistance test record, and spot check the actual measurement if necessary.
Check that all power cables, signal cables, and communication buses should be connected.
Control stations, operator stations, engineer stations, etc.
|
|
Hollysys DCS - DCS system operation problem analysis and preventive measures
1. Communication network failure: communication network faults are generally easy to occur at the contact bus and local bus, or caused by wrong address identification.
2. Node bus failure: The transmission medium of the node bus is generally coaxial cable, some use token signal transmission mode, and some use ...
|
|
Hollysys DCS——What should I pay attention to when cleaning the DCS system?
1. Power off
2. Cleaning the ash can not only clean the surface, but also clean the internal card key of the controller
3. If there is a supporting UPS, open the UPS and clean the ashes
4. After cleaning the ash, check whether the card and relay are loose, and tighten them if they are loose
5. The relays with frequent actions should be cleaned regularly.
|
|
HollySys PLC - What are the design requirements that need to be met for PLC programs?
Simplicity
Make the PLC program as simple as possible. Simplicity means using a standardized procedural framework as much as possible and using simple instructions as much as possible.
If you want the program to be simple, in a big way, you should optimize the program structure, simplify the program with process control instructions, and ...
|
|
Hollysys PLC - the design specification of PLC program
(1) Select the appropriate PLC model and I/O points, and select the special function module when there are special function requirements.
(2) Familiar with the selected PLC programming instructions and compilation software.
(3) Carry out soft component planning, including internal relays, holding relays, data registers, ...
|
|
Hollysys PLC - PLC maintenance and use skills
With the development of society, PLC programmable controller has been widely used in industrial production, but its maintenance and overhaul methods and skills, many engineers are not lawful, the following is to introduce the experience and skills of PLC use process.
1. PLC input and output
A ...
|
|
Hollysys PLC - the control function of PLC
(1) Computing function
The computing functions of a simple PLC include logic operation, timing and counting functions; The operation functions of ordinary PLC also include data shift, comparison and other calculation functions; More complex arithmetic functions include algebraic operations, data transmission, etc.; There are also analog PIDs in large PLCs.
|
|
Hollysys PLC - Classification and application of PLC
1. Switch logic control
Switching logic control is the basis of PLC. It is the first use case and the most extensive of all. Replace the previous relay circuit control and realize logic sequence control; It can be used for the control of stand-alone equipment, and can also be used for group control and ...
|
|
Hollysys PLC – PLC programming advice
(1) When the PLC and the host computer (or touch screen) form a monitoring system, there are many times when there are "manual", "automatic" and other control modes on the screen (generally when there is only one multiple). You can use the "MOV" command in the program. For example, when "manual" is selected, the constant 1 MO ...
|
|
Hollysys signed a strategic cooperation agreement with Jinan Iron and Steel International in Jinan
Hangzhou Hollysys Automation Co., Ltd. (hereinafter referred to as Hanghe) and Jinan Iron and Steel Group International Engineering Technology Co., Ltd. (hereinafter referred to as Jinan Iron and Steel International) signed a strategic cooperation agreement in Jinan. Luan Yuandi, Deputy General Manager of Jinan Iron and Steel International, Sun Jiaying, Director of the Automation Division, and Liu Xinjie, Director of the Automation Office...
|
|