Hollysys DCS - the debugging scheme of DCS system

Create Date: 2024-8-30 12:03:23|Source: HollySys/HollySys

1. Check before power-on

If the cable insulation resistance meets the requirements (greater than 5M ohms), check the cable insulation resistance test record, and spot check the actual measurement if necessary.

Check that all power cables, signal cables, and communication buses should be connected.

The model and location of the plug-in card, adapter and its interface in each chassis such as the control station, operator station, and engineer station are correct.

The setting knob of each card is in the correct position.

The power supply unit and the power switch on the plug-in card are in the "OFF" position, and all fuses are intact.

All connecting screws in the cabinet should be firm and not loose.

Grounding System Grounding Resistance Test:

l Remove the "MG" and "CG" grounding buses from the grounding floor of the control room, and measure the base grounding resistance with a grounding resistance tester respectively, which should meet the design requirements (less than 10 ohms).

l Use a multimeter to check whether the grounding busbar of each cabinet is plugged in with the "MG" and "CG" grounding plates respectively.

l The insulation resistance between "MG" and "CG" should meet the requirements of GBJ93-86 specification (greater than 5M ohms).

UPS Power Test:

l Check that the power panel and the power switch are in the "OFF" position.

l The UPS will be put into operation by the electrical personnel, and the voltage before the measurement and transmission to the main power switch of the instrument power panel should be 220VAC±10%, 50Hz±2%.

l UPS uninterrupted test by electrical personnel. (After full load is put into use, repeat this test, and the battery power supply time should not be less than 30 minutes)

2. Power-on test

Carry out the following power-on tests on each cabinet and console one by one:

l Put the power switch in the cabinet in the power panel in the "ON" position, and use a digital multimeter to check the voltage before the main power switch of the cabinet, which should be 220±22VAC.

l Confirm that each card in the cabinet (except the power card) has been unplugged from the card holder, and then put the main power switch of the cabinet, the power supply unit, and the power switch on the power card to "ON" in turn, and measure the DC voltage output with a digital voltmeter, which should meet the requirements of the manufacturer's manual (5.1±0.02V, -12±0.3V, 12±0.3V, 24 VDC). If the allowable deviation range is exceeded, the adjustment is made.

l Carry out the manual switching test of dual power supply.

l Turn on the power supply of each nested fan, signal converter fan, hard disk drive fan, cabinet roof, door fan, etc., and check each fan, which should run normally.

l Check whether the power alarm circuit is working.

3. Start and load the system

l Engineer station start program.

l Operating station starting procedure.

l Control station starts: After the power is turned on, the system status screen is called up, and the confirmed status is normal.

l Loading operation.

The loading procedures of each station are detailed in the manual.

4. System diagnosis and redundancy test

(1) Call up the system diagnosis screen and perform diagnostic inspections on each station and station.

(2) For various redundant modules of the system, artificially simulate faults (by cutting off the power supply; Unplug the power plug, plug-in card, etc.), observe whether the spare module can run within the specified time, and observe the switching process on the operating table to observe whether the automatic switching process is normal.

l Communication redundancy test

l Redundancy test of dual controller

l Operation station redundancy test

l Printer hot standby test

5. Picture test

1) Flowchart screen test:

a) The process screen is displayed in the form of P&I diagram, and the number of pages and the content of the screen should meet the configuration requirements.

b) Static display check:

* Check the position, color, and text description of the title.

* The shape, size, position, and color of the graphic.

*Width, location, color and inlet and outlet joints of the process line.

* Measure the symbol, text, size, position, and color of the variables.

* Arrow, width, position, content of the gauge signal.

* Page connection symbols of shape, size, position, color, in and out arrows.

*The engineering survey unit meets the design requirements.

c) Screen dynamic display check:

*The change value of the measured variable should be within the accuracy range that the system can recognize.

*Color change of valve and pump operating status.

* The alarm status changes and should be the correct priority level.

d) Select a loop from the process screen and perform an experiment to adjust the setpoint, control mode (auto/manual), and manual output.

2) General picture test

a) Confirm that the overview screen has been configured according to the configuration data sheet.

b) Check the correct configuration of the groups and units in each area of the general picture picture.

3) Group screen debugging

a) Confirm that the loops in the group screen are the same as those described in the general view.

b)that the individual measured values, set values, and outputs in analog and digital form are correctly configured.

c) Perform a test to change the setpoint, control mode and output.

d) For the group screen of the digital or program loop, by changing its state, the color of the observation block or the change of the status display information should meet the configuration requirements.

e) Confirm the configuration of the selectable functions: high and low limit alarms, deviation alarms, output limits, adjustment parameters, power failure restart modes, cascade or feedforward loop information, filter parameters, and other information related to the loop or digital program.

6. Function test of operating keyboard

1) Confirm that the function keys directly operated by the operator are operating normally, can call up various displays, operate each loop (including control mode, setting value, setting cascade, output signal adjustment, etc.), alarm confirmation, and execute various functions of the printer.

2) Confirm that the operator's keypad activated by the key lock or password is operating normally, and can change the measurement range, alarm value and output signal limit.

7. Report testing for printers and duplicators

1) Check that the printer can print the information specified by the operating station.

2) Confirm that the alarm printing occurs automatically, and the order is the same as that of the alarm summary screen.

3) Check that the print of the "confirm" or "restore" time is the same as the actual occurrence time.

4) Check that if the number of alarms is faster than the printing speed, the alarm printing will not be lost.

5) Check that if the printer fails, the alarm points during this time can still be printed correctly after repair.

6) Confirm that the interlock alarm coming from the PLC has the first signal display in the specified group (the whole interlock is divided into groups) and has a resolution of 300ms.

7) Confirm that the copy function can make a hard copy of any screen displayed on each CRT screen, and at least one screen per CRT during the test.

8) Confirm that the report can be printed in the configured format.

9) Check the automatic printing function of hourly report, shift report, daily report, and monthly report.

10) Check that the report data can be instantaneous values, average values, and cumulative values for the previous 30 hours (and include hourly averages)

8. System recorder test

Confirm that the logger is programmed and functions as designed.

Add at least one input signal to each recorder (3 strokes) to check whether it can be recorded through the configured channel.

9. DCS channel test

After the above-mentioned DCS configuration and function test, 100% channel test is carried out, that is, the signal is added from the I/O input terminal, the indication value is observed on the CRT of the operation station, the signal is output from the operation station, and the output value is measured at the I/O output terminal, and its deviation should meet the accuracy requirements (0.2 level).

Test method: According to the loop diagram, the input and output signals are grouped and debugged according to analog, digital, thermocouple, thermal resistance and other types.

During the debugging process, pay attention to the branching, indication, recording, alarm and other simultaneous tests of the circuit.

After each circuit (or part of it) is debugged, mark the circuit with a color pen and fill in the debugging record in time.

For sequence and interlocking loop test: according to the logic diagram, input signal check sequence and interlocking action should meet the design requirements. If not, check the sequential table configuration.
Hollysys DCS - the debugging scheme of DCS system

More on that
Hollysys PLC - the use of PLC serial port communication Hollysys PLC - the use of PLC serial port communication

Serial communication is done using 3 wires: (1) ground, (2) sending, and (3) receiving. Since serial communication is asynchronous, ports are capable of sending data on one wire and receiving data on the other. Other threads are used for handshakes, but are not required. Serial communication is the heaviest ...

Common fault parts and maintenance of Hollysys PLC Common fault parts and maintenance of Hollysys PLC

1. Lack of motivation It may sound simple, but it's good to check the simple stuff first. Thoroughly inspect all power connections and cables for damage that could cause a short circuit. Make sure your power supply is functioning properly. Use a voltmeter to check if the grounding and voltage are correct. 2. Bad ...

Steps on how Hollysys DCS works on a computer Steps on how Hollysys DCS works on a computer

1. Confirm that the new computer has relevant interfaces and can be used normally, and Hollysys DCS software can run on the computer operating system 2. Device and Lisi DCS software, dongle, and related drivers (mainly redundant network cards, data hard disks, etc.) 3. Set up ...

Hollysys PLC - Introduction to the functions and application fields of PLC Hollysys PLC - Introduction to the functions and application fields of PLC

1. The function of PLC PLC is a general industrial automatic control device with microprocessor as the core, integrating computer technology, automatic control technology and communication technology, which has high reliability, small size, strong function, simple program design, flexible and universal and maintenance methods.

Hollysys PLC - Electrical troubleshooting of PLC control loop Hollysys PLC - Electrical troubleshooting of PLC control loop

In general, PLCs are extremely reliable devices with a very low failure rate. The probability of hardware damage such as the CPU of the PLC or software running errors is almost zero; If the PLC input point is not caused by strong current intrusion, it will hardly be damaged; The normally open point of the PLC output relay, if it is not a short circuit of the peripheral load ...

Century Qualcomm and Hollysys reached a strategic cooperation Century Qualcomm and Hollysys reached a strategic cooperation

With the inclusion of "exploring the construction of digital twin cities" in the 14th Five-Year Plan, the field of intelligent transportation is being endowed with more new business value. Recently, Century Qualcomm and Hollysys reached a strategic cooperation, based on the principle of "giving full play to advantages, mutual promotion, long-term cooperation, mutual benefit and win-win", ...

Hollysys - Contribute to China's green development "Yizhuang Power" Hollysys - Contribute to China's green development "Yizhuang Power"

Facing China's "double carbon" strategic goals, the Beijing Economic and Technological Development Zone is guiding a large number of enterprises to explore the implementation plan of "carbon peak" and "carbon neutrality", and strive to build a number of green factories, green products and green supply chains. Recently, enterprises in the zone and Lisi Group signed a contract for the first time in China to use CO (dioxide...

Hollysys PLC - a component of the PLC control cabinet Hollysys PLC - a component of the PLC control cabinet

1. Open empty A master air switch that is the power control for the entire cabinet. 2. Power supply A 24VDC switching power supply. 3、PLC This should be chosen according to the needs of the project. If the scale of the project is small, the integrated PLC can be used directly; If the item ...

Hollysys PLC - Six Fault Types of PLC and Troubleshooting Methods (1-3) Hollysys PLC - Six Fault Types of PLC and Troubleshooting Methods (1-3)

First, the type of failure of the PLC. 1. External equipment failure. External equipment refers to various switches, sensors, actuators, loads, etc., which are directly connected with the PLC operation process. The failure of these equipment will directly affect the control function of the PLC system. Therefore...

Hollysys DCS - DCS system operation problem analysis and preventive measures Hollysys DCS - DCS system operation problem analysis and preventive measures

1. Communication network failure: communication network faults are generally easy to occur at the contact bus and local bus, or caused by wrong address identification. 2. Node bus failure: The transmission medium of the node bus is generally coaxial cable, some use token signal transmission mode, and some use ...

Hollysys PLC - Calculation of the amount of pulses in PLC Hollysys PLC - Calculation of the amount of pulses in PLC

The control of pulse amount is mostly used for angle control, distance control, position control and so on of stepper motor and servo motor. The following is an example of a stepper motor to illustrate each control mode. 1. Angle control of stepper motor. First of all, it is necessary to clarify the number of subdivisions of the stepper motor, and then determine the stepper ...

Hollysys DCS - Introduction to I/O in DCS control system Hollysys DCS - Introduction to I/O in DCS control system

The control system needs to establish the input and output channels of the signals, which is called I/O. The I/O in a DCS is generally modular, with one or more I/O channels on one I/O module for connecting sensors and actuators (control valves). The control unit of the DCS: a process control station is ...

Hollysys PLC - PLC serial communication knowledge Hollysys PLC - PLC serial communication knowledge

1. What is serial communication? Serial is a very versatile protocol for device communication on a computer (not to be confused with Universal Serial Bus or USB). Most computers contain two serial ports based on RS232. The serial port is also an instrument ...

Hollysys DCS - How to deal with DCS system failure? Hollysys DCS - How to deal with DCS system failure?

1. View the data on the monitoring screen When the following situations occur, it means that there is a problem with the control system, and the microcomputer maintenance personnel should be notified immediately for maintenance, and the operator should go to the site to deal with it. (1) Frequently changing data does not change for a long time, and several or all data do not ...

Hollysys PLC - common causes and treatment methods of PLC failures in operation Hollysys PLC - common causes and treatment methods of PLC failures in operation

1. Peripheral circuit component failure This type of failure often occurs in the failure of the PLC after a certain period of work. In the PLC control loop, if there is a component damage fault, the PLC control system will immediately and automatically stop working. The input circuit is a PLC that accepts switching quantities, analog ...

Hollysys PLC - the six application functions of PLC Hollysys PLC - the six application functions of PLC

1. It is used for switching control The ability of PLC to manipulate switching quantities is very strong. The number of points in and out of the control, less than a dozen points, dozens of points, more can be hundreds, thousands, or even tens of thousands of points, because it can be networked, the number of points is almost unlimited, no matter how many points can be controlled, the control ...

The difference between Lysys plc - RS232 interface and RS485 interface The difference between Lysys plc - RS232 interface and RS485 interface

1. The physical structure of the interface 1. RS232 interface: One of the computer communication interfaces, usually RS-232 interface in 9 pin (DB-9) or 25 pin (DB-25) form, generally there will be two sets of RS-232 interfaces on personal computers, respectively called COM ...

Hollysys safety barriers won excellent products Hollysys safety barriers won excellent products

On December 18, 2020, the "8th Member Congress and 2020 Zhejiang Enterprise Leaders Summit" hosted by Zhejiang Enterprise Confederation, Entrepreneur Association and Industrial Economics Federation (hereinafter referred to as the "Three Associations" of Zhejiang Province) was held in Hangzhou. At the conference, the top 100 in Zhejiang Province in 2020 were commended.

Hollysys debuted at the XCon2022 Security Focus Information Security Technology Summit Hollysys debuted at the XCon2022 Security Focus Information Security Technology Summit

On September 19, 2022, the XCon2022 Security Focus Information Security Technology Summit was successfully held in Beijing. More than 10 technical experts, heads of security departments, and front-line security experts from well-known domestic network security enterprises shared in-depth topics at the meeting.

Hollysys PLC - the characteristics of the working process of PLC Hollysys PLC - the characteristics of the working process of PLC

(1) The PLC adopts the working mode of centralized sampling and centralized output, which reduces the influence of external interference. (2) The working process of PLC is the process of cyclic scanning, and the length of cyclic scanning time depends on the speed of instruction execution, the length of the user program and other factors. (3) Output ...

CATEGORIES BYPASS
Customer Service Center

Online Consultation:QQ


ContactContact

Contact: Manager Huang

Contact QQ: 3271883383

Contact number: 13522565663


Scan the code to add WeChat (please save the picture first on the mobile phone)

working hoursworking hours

Weekdays: 9:00-17:00

Holidays: Only emergencies are handled

Contact us

Contact us

Contact number QQ consultation
QQ consultation

3271883383

Company address
Back to top